We are excited to share all our summer projects are on schedule and staying within the budget. We have had projects at the High School, Cedar View Elementary, Red Hawk Intermediate, and Beach Elementary.
Below is more information on where we are at on each of these projects:
High School
- Classrooms are close to completion
- The expanded cafeteria space is moving into the final stages
- New offices are beginning to receive furniture
- The new entryway to the office area has begun
- Track resurfacing begins at Red Hawk Stadium will begin next week
Cedar View
- Secured entryway and new office space is in progress
- Classroom finishes and mechanical work is on schedule
Red Hawk Intermediate
- Much of the new pavement is poured around the building
- Sanitary plumbing throughout the building is being replaced
- Classroom renovations continue to move on schedule
Beach Elementary
The planning team has begun working with an architect and builder to identify the best layout and building features for the new building sections of Beach Elementary.
The gym, cafeteria, kitchen, and special rooms are expected to be incorporated into the new building.